Barka I Expansion Project Phase II IWP
Project Details
| Offtaker | Project Company | Owner's Engineer | EPC |
![]() |
![]() |
![]() |
- 56,826 m3/d Potable Water from Seawater
- Project Cost $80 million USD
- Actual Commercial Operation Dates for 3 Project Phases - 31st October 2015, 5th November 2015, 25th February 2016
- The 2nd COD date for 10 MIGD was achieved on time, in 10 months from NTP to COD
- Nominated for Global Water Intelligence Desalination Project of the Year 2016
Desalination Technology
- 200µm Strainers, Pall Microfiltration, Hydranautics RO, DWEER Energy Recovery, Lime & CO2 Remineralisation
BryTech Solutions Services
- BryTech Solutions provided process design and design management services to the EPC Contractor, Osmoflo as well as playing a lead fole in commissioning, performance testing and troubleshooting during the first year of operation.